Day rates with shared surplus

A job is figured for a number of days and the crew is paid for those days however fast they finish — whatever is left over goes back to them, split by hours worked. Finishing early is worth money to the men who do it.

The operating system for post-frame and barndominium builders.

Part of Crew Pay & Payroll
What it is

Each man earns his tier's day rate for every day he works. The pool is the days you figured, multiplied by what a day of that crew costs — every man's tier rate plus the equipment allowance. Whatever is left after the day rates and the equipment is shared back out by hours worked. Crews paid by the job is how post-frame buildings actually get put up, and this is the operating system for post-frame and barndominium builders paying them that way. Paying by the hour instead? The same surplus sits on top of an hourly wage on hourly pay with shared surplus. Or give each man a share of the labour price — the same money however fast the job goes.

Also called: pay crew by the day · finish early bonus · labour pool · incentive pay for crews · profit share with the crew

See it, piece by piece
01

Pay the crew for the days you figured, however fast they finish

A job is figured for a number of days. The pool is those days multiplied by what a day of that crew costs — every man's tier rate plus the equipment allowance. The crew earns its day rates for the days actually worked, and whatever is left in the pool goes back to them. Finish a three-day build in two and the crew keeps the day you saved, and you are onto the next job a day sooner.

Pay Structure — Run the numbers on a job
Run the numbers on a job

Nothing here is saved. Use the placeholder workers or pick people off your roster, set the days and the hours, and watch what day rates + shared surplus does to the numbers.

Reset
Days figured
7
Finished
−−2+
finished 2 days early
Days on site
5
7 figured − 2
This crew’s day
$2,060
$1,760 tiers + $300
Total pool
$14,420
7 figured × $2,060
Surplus to share
$4,495
$899 each if hours are equal
WorkerTier12345HrsDaysDay ratesSurplus bonusTakes home
Wes Hartzler+Tier 188888405$2,500.00+$956.39$3,456.39
Marlin Zook+Tier 288888405$2,000.00+$956.38$2,956.38
Chet Ober+Tier 388888405$1,750.00+$956.38$2,706.38
Levi Stauffer+Tier 488488365$1,215.00+$860.74$2,075.74
Duane Yoder+Tier 588808324$960.00+$765.11$1,725.11
+ Add a worker
Crew is paid
$12,920
Per day on site
$2,584
Works out at
$68.72/hr
Crew hours
188
7 days figured, 5 on site — finished 2 days earlyThe crew keeps the $4,495 surplus — that is $2,248 for each day they saved.
Seven days figured, five on site — and the $4,495 that goes back to the crew. Real screen · sample data.
Without it

A build you priced for three days takes three days every time, because nothing about finishing on Wednesday ever reaches the men who would have to do it.

Why we built it

Men work harder for money they can see coming to them. The pool is fixed at the days you figured, not recalculated at the days worked, so the money a fast build frees up has somewhere to land — you are buying the empty day back instead of watching the work stretch to fill it.

02

One ladder of day rates, priced once, instead of a rate per man

Tiers are one list with a day rate each, edited in place on the Crews tab and retired rather than deleted so old payouts keep their arithmetic. A tier is a rate, not a rank: two men on Tier 2 earn the same day whatever their job title. That is the point of paying this way instead of negotiating with every man separately.

Pay tiers
Pay tiers

What one full day is worth at each tier. Crews paid by day rates are priced from these, and a person earns their tier’s rate for every day they work.

All tiers
$1,760
Tier 1$500/day
Tier 2$400/day
Tier 3$350/day
Tier 4$270/day
Tier 5$240/day
+ Add tier
Five tiers and what one full day is worth at each — $1,760 of crew before equipment. Real screen · sample data.
Without it

Every man's rate lives in a separate conversation, and nobody can tell you what one day of Crew A costs without adding five numbers off the top of their head.

Why we built it

A man knows exactly where he stands, and what the next step up is worth. A crew's day becomes one number you can price a job against, and raising a man is moving him up a rung — not reopening a negotiation every spring.

Sound familiar?“crew stretches a two-day job into three”
03

Every man on the crew sits on a rung

Try it

The crew card names who is on it and the tier each one is on — Tier 1 · $500, Tier 2 · $400 — so a crew's day is read off the card, not assembled in somebody's head. The pool is priced from the crew as established, not from whoever turned up. Getting a man onto the books in the first place, with his details and his record, happens on the Team Members list.

Crew card expanded
2
Projects
18
Stages Done
1
In Progress
-0.8d
Avg Variance
Current Project
Wenger 40×60 Shop
Framing — Day 3
Members (4)
MZ
Marlin ZookLEADER
(717) 555-0143 · marlin@stonebridge.demo.invalid
PlansTier 1 · $500
DE
Dwayne Esh
(717) 555-0168
PlansTier 2 · $400Leader
CL
Curtis Lapp
(717) 555-0117
PlansTier 3 · $350Leader
NB
Nelson Beiler
(717) 555-0192
PlansTier 4 · $270Leader
Assigned Projects (2)
Wenger 40×60 Shop4/7 stages
Beiler Barndominium0/6 stages
Crew B — four men, each with his tier and his rate on the row. Real screen · sample data.
Without it

One man is off Tuesday, the pool quietly drops by his day rate, and the four who did turn up share less money for doing more work.

Why we built it

The four who covered for a sick man get paid for it — that is what keeps a crew loyal to each other and to you. Pricing the pool off the crew you meant to send means an empty seat lands in the surplus and goes back to the men who did the work.

04

What one day of that crew costs, worked out once

One of every tier working, plus what it costs to put them on the road: $1,760 of day rates and $300 of fuel and equipment is a $2,060 day. Every pool on every job that crew touches is built from that one figure.

What a day costs
1What a day costs

One of every tier working, plus what it costs to put them on the road. A real crew is whoever you send — the sandbox below prices the one you build.

Tier 1
$500
Tier 2
$400
Tier 3
$350
Tier 4
$270
Tier 5
$240
One of each tier
$1,760
+
Fuel & equipment / day
$300
=
Day at these rates
$2,060
Five tier rates plus the road cost — the $2,060 day. Real screen · sample data.
Without it

You are still pricing labour off a day rate you worked out in the spring, and nobody has told the estimate that fuel went up in June.

Why we built it

The owner needs one honest number for a crew day, not five rates and a guess at fuel. Holding the day as tiers plus equipment means moving one rung re-prices every job figured after it, so no crew quietly runs at last year's cost.

Sound familiar?“no reason for my guys to finish early”
05

Fuel, equipment and the truck are in the crew day

Try it

A per-day allowance is added to the tier rates to price one crew day, so the pool is funded at what a day actually costs rather than at wages alone. It is charged per crew day, not per man, and it comes off your side of the ledger at the days actually worked. Leave it out and a job one day over reports money still sitting in the pool while you are down.

Crew labour source
Labor Source
Type
Pay model
Equipment / day$300
Full day over6hrs
Working daysSMTWTFSSame as the company

Internal — employees log hours & expenses from the field view.

The pay model, the equipment allowance and the full-day rule, set on the crew itself. Real screen · sample data.
Without it

The truck, the fuel and the blades come out of your pocket all week and never once appear in the number you call the labour cost.

Why we built it

The truck and the fuel are real money, and the crew knows it — leaving them out makes the pool look richer than it is. The allowance belongs to the crew, so the outfit hauling a compressor is not priced like the two-man crew in a van.

06

What you are committing to before anyone picks up a hammer

Two days, four, seven, fourteen, thirty — the pool at each, with the labour and the road cost kept apart. The figure is set by the days you figure for, not the days it takes, which means you know the labour cost of the job on the day you sell it rather than the week you close it.

What a job costs at these rates
2What a job costs at these rates

The pool is fixed by the days you figure for, not the days it takes. This is what you are committing to before anyone picks up a hammer.

Figured forLabourFuel & equipmentTotal pool
2 days$3,520$600$4,120
4 days$7,040$1,200$8,240
7 days$12,320$2,100$14,420
14 days$24,640$4,200$28,840
30 days$52,800$9,000$61,800
The same crew day, projected across 2, 4, 7, 14 and 30 days figured. Real screen · sample data.
Without it

You sell the labour on a feeling, the crew takes eleven days instead of seven, and the first honest number arrives with the payroll run.

Why we built it

An owner sleeps better knowing the most a job's labour can cost before it starts. Showing the commitment as a table of days makes the bet readable before you take it — the row you pick is your ceiling.

Sound familiar?“paying straight time rewards being slow”
07

The number the crew is measured against is written on the job

Every job carries the days its labour was figured for — the number you landed on when you priced the work, off the crew, the wage and the hours the building needs. Where nobody set one, the scheduled span is used and the screen says so. The pool does not shrink when the crew comes in early — that is the entire incentive.

Build Schedule
Project / Task
Hostetler Equipment ShedCrew A
Zimmerman Horse BarnCrew B
PermittingAug 4 – Aug 18
Dirt WorkAug 18 – Aug 22
ConcreteAug 22 – Aug 28
Material DeliveryAug 28 – Sep 1
Post SetSep 1 – Sep 11
Stoltzfus ShopCrew C
Byler BarndominiumCrew A
Jul 27– Aug 2
Aug 3– Aug 9
Aug 10– Aug 16
Aug 17– Aug 23
Aug 24– Aug 30
Aug 31– Sep 6
Sep 7– Sep 13
Sep 14– Sep 20
Sep 21– Sep 27
Sep 28– Oct 4
Oct 5– Oct 11
Oct 12– Oct 18
Oct 19– Oct 25
Oct 26– Nov 1
TODAY
Permitting 4/4
Post Set 3/6
Siding / Roofing 0/11
46% • 38d
Permitting+3d
Concrete
Post Set0/6
Permitting 1/4
Framing 0/6
Siding / Roofing 0/11
Permitting 0/4
Slab / Foundation 0/6
Post Set 0/6
Siding / Roofing 0/11
Shutdown week — Crew B
OVERLAP
The scheduled span — what the pool falls back to when nobody wrote a figure. Real screen · sample data.
Without it

You sold the labour as twelve days in your head, and by the time the payout matters the argument is about whose memory to trust.

Why we built it

A crew will only chase a target that was set before they started. Writing the figure on the job up front makes it a deal, not a verdict handed down at the end — and the screen says when it fell back to the schedule.

08

A day is a day over six hours — and a long day earns no more

Try it

At or above the threshold, the full day rate is earned. Below it the day prorates, and it can never come out above the rate. Two shifts on one date collapse into one day's attendance. Both numbers are settings, because the next builder does not run a six-hour day. It is a rule anyone on the crew can state in one sentence, which is what makes it stick.

Run the numbers on a job
3Run the numbers on a job

Nothing here is saved. Use the placeholder workers or pick people off your roster, set the days and the hours, and watch what day rates + shared surplus does to the numbers.

Days figured
7
Finished
0
finished on time
Days on site
7
7 figured + 0
This crew's day
$2,060
$1,760 tiers + $300
Total pool
$14,420
7 figured × $2,060
Surplus to share
$360
$72 each if hours are equal
WorkerRate1234567HrsDaysDay ratesSurplus bonusTakes home
Nate Ottinger597$3,500.00+$77.24$3,577.24
Bess Kowalczyk567$2,800.00+$73.31$2,873.31
Otis Bramble587$2,450.00+$75.93$2,525.93
Sherman Ealy567$1,890.00+$73.31$1,963.31
Levi Yutzy465.5$1,320.00+$60.22$1,380.22
Crew is paid
$12,320
Per day on site
$1,760
Works out at
$44.80/hr
Crew hours
275
7 days figured, 7 on site — finished on time
Finishing inside the figured days leaves a surplus, and it goes back to the crew split by hours worked — so being there matters more than which tier you are on.
Pool — 7 days figured$14,420.00
Day rates earned — 7 days on site$11,960.00
Fuel & equipment — 7 days$2,100.00
Surplus shared out$360.00
Put 4 in a cell and the day prorates; put 12 in and the day rate does not move. Real screen · sample data.
Without it

Someone leaves at two in the afternoon and you spend the drive home deciding whether that counted as a day — and you will decide differently next month.

Why we built it

A rule anyone can say in one sentence ends the Friday argument about part-days. The rate is neither capped at the top nor docked at the edge, and a man who stays late is not working for free — the extra hours lift his share of the surplus.

Sound familiar?“want to share the savings with the crew but can't work out the math”
09

The pool only turns into money once somebody has worked it

Every figure on the payout is downstream of hours somebody actually logged. A job with nothing logged against it has no surplus at all — the pool is money you set aside, not money anyone is owed yet. The hours this splits by are not written down at the end of the week: they come off one tap in and one tap out on the crew's own phones, which is also where the job and the stage get settled.

Approvals
Approvals
Timesheets and expenses your crews and subs submitted, waiting on you.
7
pending
$1,104.60 in expenses
Wenger 40×60 Shop
Approve all (4)
Posts & framing
2026-08-24 · Crew B · 4 on site
32 hrs
Posts & framing
2026-08-25 · Crew B · 4 on site
30 hrs
materials · Zimmerman Supply
2026-08-25 · Crew B · Posts & framing
$486.20
fuel · Sheetz
2026-08-25 · Dwayne Esh · reimbursable
$78.40
Stoltzfus Equipment Storage
Approve all (3)
Roof steel
2026-08-24 · Ridge Overhead · 2 on site
620 units
rental · Keystone Equipment
2026-08-25 · Ridge Overhead · Roof steel
$540.00
Site prep
2026-08-26 · Crew C · 3 on site
18 hrs
Timesheets waiting on you — the input every figure on the payout comes from. Real screen · sample data.
Without it

A job set up on Monday and not begun shows a five-figure bonus against somebody's name, he sees it, and you spend a week explaining a number the software invented.

Why we built it

Nobody wants to see a bonus next to his name that was never real. The surplus is only what the crew earns back by working, so with nothing logged there is nothing to share — an untouched pool is money set aside, not money owed.

Sound familiar?“how do I pay a crew fairly when one guy missed a day”
10

The surplus splits by hours worked, not by tier

The tier decides what a man earns; presence decides what he shares. Once day rates and equipment come out of the pool, the rest is divided strictly by each man's share of the crew's hours — in real figures, on the job's payout screen. The man who missed a day and worked half of another takes a visibly smaller slice than the man who was there for all of it, the fairness question that decides whether the scheme survives contact with a real crew.

Crew payout
Crew payout
Crew A · figured for 12 days · 361h logged over 11 days
Refresh
Pool
$21,840
Day rates earned
$15,833
Fuel & equipment
$3,300
Surplus shared
$2,708
WhoTierHoursDaysDay ratesSurplusOwed
Levi YutzyTier 19611$5,500.00$720.00$6,220.00
Dwayne MillerTier 29210.5$4,200.00$690.00$4,890.00
Curt HershbergerTier 38810$3,500.00$660.00$4,160.00
Andre OcampoTier 4859.75$2,632.50$637.50$3,270.00
Total to the crew$18,540.00

Hours come from what the crew logged on their field links. Day rates are earned per day worked; the surplus is split by share of hours, so being there is what moves it.

Day rates track the tier; the Surplus column tracks the hours beside it. Real screen · sample data.
Without it

One man was off Thursday and half of Friday, and the moment the bonus is split evenly the other four stop believing in the scheme.

Why we built it

Fair is what keeps a crew together: the man who was there all week takes more than the man who wasn't. Splitting on the hours they already clocked means nobody has to play judge, and the per-man column can be handed to the crew as the answer.

11

What a man takes home is two numbers stacked

The base of every column is what his tier earned him; the block on top is his slice of the surplus. The tier sets the first number and the hours set the second, which is how a Tier 4 man who was there all seven days narrows the gap on a Tier 2 man who was not. What the job sold for is nowhere near it — contracts, invoices and change orders are shut off for both field roles on roles and permissions.

What each worker takes home
3AWhat each worker takes home
$0.0k$0.9k$1.8k$2.7k$3.6k
Nate OttingerBess KowalczykOtis BrambleSherman EalyLevi Yutzy
Day ratesSurplus
Day rates in the base, surplus stacked on top, one column per man. Real screen · sample data.
Without it

One figure on a payslip is a figure to argue with, and nobody can see which half of it working differently would have moved.

Why we built it

A man can see which part of his pay he controls this week — and that is what makes him try. Pay drawn as two blocks can be explained at a tailgate: the rung he is on, and the share he earned by showing up and finishing early.

Sound familiar?“pay my crew leader a percentage of the labour”
12

Every man sees what finishing early has paid him

Try it

On the Hours door of the crew app, What you have made splits everything paid to him into wages and surplus, shows his highest hourly wage with the lift above his base, and adds up what finishing ahead has paid him — with his biggest single surplus beside it. Only his own money, never anyone else's.

What you have made
since May 4
Highest hourly wage+$4.20/h
$28.20
$24.00 on the books
Wages
$19,500
hours × your rate
Usual hour
$26.88
all in
Shared surplus
what finishing ahead paid
Surplus booked
$2,340
Biggest
$596
Joel Nolt — 40×64 Horse Barn
Josh's money since he started — wages, surplus, and the best hour a job ever paid him. Real screen · sample data.
Without it

You pay a bonus for finishing early, but the crew never sees the sum behind it, so it is a number that turns up some weeks and not others.

Why we built it

People work for what they can see — a running total of what beating the days has paid him turns the bonus from a rumour into a reason. He feels he is earning more and getting better, because he is; for you that is a crew that pushes to beat the figure and stays another season.

13

Run long and the overrun comes out of your margin, not their pay

When the day rates and equipment come to more than the pool, there is no surplus to share, and the screen says so in those words rather than showing a negative bonus. The crew still earns its day rates. Because they are never clawed back, running long lands on your side of the ledger, and what it cost you is read on the job's profit and loss.

Payout overrun
Crew payout
Crew B · figured for 8 days · 389h logged over 11 days
Refresh
Pool
$16,480
Day rates earned
$17,750
Fuel & equipment
$3,300
Overrun
$4,570

They have gone past the 8 days this job was figured for, so there is no surplus to share. The crew still earns its day rates — the overrun comes out of your margin.

WhoTierHoursDaysDay ratesSurplusOwed
Marlin ZookTier 18811$5,500.00$0.00$5,500.00
Dwayne EshTier 28511$4,400.00$0.00$4,400.00
Curtis LappTier 38010$3,500.00$0.00$3,500.00
Nelson BeilerTier 4729$2,430.00$0.00$2,430.00
Reuben StoltzfusTier 5648$1,920.00$0.00$1,920.00
Total to the crew$17,750.00

Hours come from what the crew logged on their field links. Day rates are earned per day worked; the surplus is split by share of hours, so being there is what moves it.

Eight days figured, eleven worked — every Surplus cell at $0.00, day rates paid in full. Real screen · sample data.
Without it

A job that runs two days long is the moment a pay scheme either holds or quietly becomes the crew covering your estimate.

Why we built it

Your crew should never pay for your bad guess at the days — and they will trust the scheme because they don't. Day rates are never clawed back, so an overrun lands on the estimate and becomes a lesson in how you price labour, not a payroll fight.

Sound familiar?“crew doesn't believe the bonus is real”
14

A man with no tier is named, not silently paid nothing

Anyone on the crew without a pay tier still appears on the payout, labelled No tier, with no day rate — and the panel names him and says where to fix it. The crew cost table flags the same gap and says the crew's day rate is understated because of it. A hole in the setup that quietly pays somebody nothing is the worst way to find out about a hole in the setup.

Hours & Labour Cost — Cost by crew
Cost by crew
Day rate = the crew’s tiers + equipment
CrewDay rateDaysAt day ratePaid outActual / dayDifference
Crew A5$2,06048$98,880$104,240$2,172+$5,360
Crew B4$1,66039$64,740$62,910$1,613−$1,830
Crew C31 without a pay tier — day rate is understated$1,14022$25,080$26,405$1,200+$1,325

At day rate is what those days would cost at the crew’s tiers — the projection. Paid out is what the pooled jobs actually paid. A crew above its day rate finished inside the days its jobs were figured for and kept the surplus; below means the pool did not stretch to every day they were out. Same calculation as each job’s payout screen.

Crew C: one man without a tier, and the line saying the day rate is understated. Real screen · sample data.
Without it

A man added to the crew on Monday and forgotten in the setup turns up on payday owed nothing, and you hear about it from him.

Why we built it

Nobody should find out on payday that he was set up wrong. The gap is raised twice — beside his name on the payout and again on the crew's day rate — so an unfinished setup shows as a warning, not a wrong cheque.

15

Or pay each man a share of the labour price

Try it

Some builders pay the leader 35% of the job's labour, the next man 30%, the next 20%. That is a pay model too: each person earns his percentage of the labour on the job's estimate, and the job pays the same however fast it is done — so finishing ahead is the bonus. The calculator in Pay Structure shows it per day figured against per day worked; each man's percent is set on his crew card, and shares over 100% are refused. What isn't shared out stays with the company.

Pay Structure — Share of the labor price
Share of the labor price

Each person earns a set percentage of the job's labor price — say the leader 35%, the next 30%, the next 20%. The job pays the same however fast it's done, so finishing ahead of the days figured is the crew's bonus. What isn't shared out stays with the company.

Where it's set. In Team → Crews, set the crew's pay model to Share of the labor price, then give each person their percentage.
Where the labor price comes from. The job's estimate: the Total Labor on the approved estimate, or the latest one sent.
Who gets paid. Everyone who logged time on the job. If nobody logs time on that crew, the whole crew is paid.
Try it

A leader on 35%, the next man on 30%, the next on 20% to start. Change anything; nothing here is saved.

Labor price$
Days figured
Days it took
Finished 2 days early
PersonShareEarnsPer day figuredPer day worked
Crew leader%$1,575$315$525
Number two%$1,350$270$450
Number three%$900$180$300
Crew is paid
$3,825 · 85%
Company keeps
$675 · 15%
Early-finish bonus, leader
+$210 a day
$4,500 of labour, figured for 5 days, done in 3 — the leader's $1,575 comes to $525 a day instead of $315. Real screen · sample data.
Without it

The leader is on 35% of the labour, worked out by hand on every job, and finishing two days early never shows up as anything he can point to.

Why we built it

A man who knows his cut of every job thinks like a partner, not a clock-puncher. Putting it in dollars a day — $315 figured, $525 worked — makes the reward for finishing early something the crew can feel, and the number comes off the estimate, so nobody has to argue it.

How it works
  1. 1Set up a ladder of tiers, each with a day rate, and put every man on one.
  2. 2Switch a crew to day rates with shared surplus, with its own equipment allowance.
  3. 3Write on the job how many days its labour was figured for.
  4. 4The crew clocks in and out on their field links — that is where the hours come from.
  5. 5The pool is days figured times what a crew day costs. The crew earns its day rates for the days worked.
  6. 6Whatever is left is the surplus, split strictly by each man's share of the hours.
  7. 7Every man sees what finishing early has paid him on his own phone.
Why we built it

Labour is sold into a job as one price, and a crew's daily cost is known — so a build figured for three days carries a fixed pot of labour money. If the crew finishes in two, you are on the next job a day sooner and the saving is real. But keeping it teaches the crew that working faster is worth nothing to them. The pool pays out whether the crew takes three days or two, and the surplus from finishing early goes back to the men who created it. What a man earns is set by his tier; what he takes out of the surplus is set by the hours he actually worked — so the man who missed a day takes a visibly smaller slice than the man who was there throughout.

The problem
  • Straight time that pays the same whether a job took two days or three.
  • Builders capturing all the upside of a fast build and crews having no stake in it.
  • Splitting a bonus fairly across men on different rates and different attendance.
What you get
A crew that finishes in two days instead of three keeps the day it saved.
Your men see what beating the days put in their pocket — so they push to beat them.
You get to the next job sooner and know the labour cost up front.
The split is defensible: presence decides the share, so partial attendance shows up visibly.
What's inside
The pay ladder

A tier is a rate, not a rank in the company. Two men on the same tier earn the same day whatever their job title. The ladder is yours and open-ended — five tiers suits one builder, the next runs three or seven — and it sits on the Crews tab beside the people it prices.

What this man's day is worth

The picker sits in the crew member row, next to the Leader control, and lists each tier with its rate. It only appears for crews on day rates. Leave a man untiered and he earns no day rate — which is said on screen, not applied quietly.

Surplus split by hours, not by tier

Once day rates and equipment come out, the rest splits on hours worked. Leftover cents go to whoever worked the most, so the shares always add up to exactly the surplus. With no hours logged there is nothing to split.

A day is a day over six hours

Each crew carries its own threshold and its own standard day. Six hours or more earns the whole day rate — a long day earns no more, and a nearly-full day is not docked. Two shifts on the same date count as one day's attendance.

Fuel, equipment and the truck

The allowance is added to the crew's tier rates to price one crew day. It funds the pool at the days you figured, and comes off your side at the days actually worked. One builder runs $300 a day.

Days this job was figured for

Write the figured days on the job. Where nobody has set one, the scheduled span is used and the payout says so rather than hiding the assumption.

When the crew runs long

When the day rates and equipment come to more than the pool, the screen says the job ran long and why there is nothing to split. It never shows a negative bonus, and it never charges the overrun back against the crew.

Nobody quietly earns nothing

He still appears on the payout, labelled No tier, with no day rate. The panel names him and says where to fix it. The crew cost table flags how many people have no tier and says the day rate is understated.

Nobody has worked it, nobody has earned it

The surplus only exists once somebody has actually worked. A job that has not started cannot pay anybody, and the pool sitting there is money you have set aside.

CREW PAY

See day rates with shared surplus
on one of your own jobs.

Twenty minutes, your building, your numbers. Bring the job where “crew stretches a two-day job into three” — we will show you exactly where that stops.

leads2build.com
The frame of a post-frame building
Pay tiers
Pay tiers

What one full day is worth at each tier. Crews paid by day rates are priced from these, and a person earns their tier’s rate for every day they work.

All tiers
$1,760
Tier 1$500/day
Tier 2$400/day
Tier 3$350/day
Tier 4$270/day
Tier 5$240/day
+ Add tier
Construction Bonus Structure: Day Rates With Shared Surplus