Working days

Stage lengths are counted in the days your crew actually works, so a five-day stage never quietly runs through a weekend.

The operating system for post-frame and barndominium builders.

Part of Project Command
What it is

Type 5 days and you get five days of work. From a Monday that is five calendar days; from a Thursday it is seven. Days nobody works are shaded on the chart, so a bar sitting on a shaded band is visibly wrong. Set the working week for the company, then override it for the crew that works Saturdays or for one rush job. Built only for post-frame and barndominium builders, where the concrete crew pours on a Saturday and the framers never do.

Also called: weekends · working week · M-F · does the schedule count Saturdays · calendar days vs work days

See it, piece by piece
01

Type five days and you get five days of work, not five days on a calendar

A five-day stage starting Thursday finishes the following Wednesday, because nobody is on site Saturday or Sunday. The schedule counts in the days your crew actually works and puts the bar where it belongs. Enter it as calendar days — which is what a spreadsheet does — and the finish date is wrong before the job has begun.

Without it

A five-day stage typed on a Thursday "finishes" on Monday, the customer is told Monday, and nobody on that crew works weekends.

Why we built it

A crew boss believes a finish date only when it lands on a day his men are actually on site. Counting in working days puts the bar where the work really happens, so the date the customer hears is one the crew can hit — and you stop apologising for Saturdays that were never real.

Sound familiar?“my schedule counts weekends as work days”
02

Days nobody works are shaded, so an impossible date looks impossible

Non-working days draw as bands behind the bars at day and week zoom, with Saturday and Sunday merged into one. A stage sitting on a shaded band is visibly wrong, which is what makes the schedule readable at a glance rather than something you audit stage by stage. At quarter and year zoom the shading drops away, where a weekend would be a sliver.

Build Schedule
Project / Task
Hostetler Equipment ShedCrew A
Zimmerman Horse BarnCrew B
PermittingAug 4 – Aug 18
Dirt WorkAug 18 – Aug 22
ConcreteAug 22 – Aug 28
Material DeliveryAug 28 – Sep 1
Post SetSep 1 – Sep 11
Stoltzfus ShopCrew C
Byler BarndominiumCrew A
Jul 27– Aug 2
Aug 3– Aug 9
Aug 10– Aug 16
Aug 17– Aug 23
Aug 24– Aug 30
Aug 31– Sep 6
Sep 7– Sep 13
Sep 14– Sep 20
Sep 21– Sep 27
Sep 28– Oct 4
Oct 5– Oct 11
Oct 12– Oct 18
Oct 19– Oct 25
Oct 26– Nov 1
TODAY
Permitting 4/4
Post Set 3/6
Siding / Roofing 0/11
46% • 38d
Permitting+3d
Concrete
Post Set0/6
Permitting 1/4
Framing 0/6
Siding / Roofing 0/11
Permitting 0/4
Slab / Foundation 0/6
Post Set 0/6
Siding / Roofing 0/11
Shutdown week — Crew B
OVERLAP
The pale vertical bands behind the bars are Saturdays and Sundays. Real screen · sample data.
Without it

Nobody spots the stage booked across a holiday weekend until the crew asks why they're on the calendar for Sunday.

Why we built it

The office reads the board from across the room, and a bar crossing a grey band is a problem anyone can point at. That is what lets people trust the dates instead of auditing them stage by stage. At quarter and year zoom the bands drop away, because seven slivers to an inch is noise.

Sound familiar?“the finish date is always wrong by a week”
03

One weekend counted wrong does not drift the whole build

Stages chain, so a weekend counted as work near the start pushes everything after it. Six stages in, a build could drift by more than a week before anyone lifted a hammer — and the customer has already been given a completion date that was never possible. Counting in working days stops the drift at the source.

Without it

One weekend counted as work in Permitting pushes every later stage, and the build is a week late on paper before anyone lifts a hammer.

Why we built it

The customer remembers the first finish date you gave, so it has to be right the first time. Counting in working days fixes the error where it starts, before it rides down six chained stages and turns into a week of slip you have to explain.

Sound familiar?“5 day stage ends on a Sunday”
04

Your concrete sub works Saturdays; your framing crew doesn't

Set the working week once for the company, override it on the crew that works Saturdays, and override it again on the one rush job that has to run through a weekend. Each level shows the week it inherits, so "same as the company" has a visible consequence instead of something you go and look up. The last remaining day cannot be switched off — a crew that works no days cannot be scheduled at all.

Working days on this job
Working days on this job
MonTueWedThuFriSatSun
Same as Crew A

Stage durations on this job are counted in these days. Shaded columns on the schedule are days nobody works.

Saturday lit up with the rest of the week, and the inherit switch showing this job no longer follows Crew A. Real screen · sample data.
Without it

One company calendar says nobody works Saturday, so the concrete crew's Saturday pours live on a separate whiteboard the schedule never sees.

Why we built it

Crews don't all keep the same week — the concrete crew pours Saturday mornings, the framers never do — and each crew boss wants a schedule that knows it. Company, then crew, then job, first one set wins, so a rush job can run through a weekend without moving anyone else's dates. Each level shows what it inherits, so "same as the company" is visible instead of assumed.

Sound familiar?“does this thing know my crew doesn't work Saturdays”
05

A start date picked on a Saturday rolls to Monday, and says so

Picking a Saturday used to schedule a crew onto a Saturday. Now the date rolls forward to the next working day and the field tells you that it did. Chaining one stage onto the end of the one before it does the same.

Without it

Picking the 12th off the calendar books the framers on a Saturday, and they find out on Friday afternoon.

Why we built it

A man told to show up on a day he doesn't work stops trusting the schedule. Rolling a Saturday pick forward to the next working day — and saying so on the field — means the office never books a crew onto a day off by accident, and chained stages land the same way.

How it works
  1. 1Set the working week for the company once.
  2. 2Override it on a crew that works Saturdays, or on one rush job.
  3. 3Type a stage's length in working days.
  4. 4A start picked on a Saturday rolls to Monday, and the field says so.
  5. 5Non-working days draw as shaded bands behind the bars.
Why we built it

Stage lengths were counted in calendar days, so a five-day stage starting Thursday was scheduled to finish Monday — straight through a weekend nobody works. Because each stage starts when the last one ends, every later stage inherited the error, and a six-stage build had drifted more than a week before anyone lifted a hammer. Crews were told to show up on Saturdays that were never real, and customers were given completion dates the plan could not hit.

The problem
  • Stage durations counted in calendar days producing impossible dates
  • Chained stages compounding the weekend error across a whole build
  • No way to say one crew works Saturdays and another doesn't
What you get
Typed durations land on dates the crew will actually be on site
Errors stop compounding down the stage chain
Saturday crews and Mon-Fri crews coexist on one board
Made for post-frame crews that don't all keep the same week
What's inside
Company, crew and job working weeks

Three levels, and the most specific one wins. The company setting is the floor, a crew can override it, and one job can override that. Each picker shows the week it would inherit, so "same as the company" has a visible consequence instead of something you go and look up.

The seven-day week picker

A row of seven day toggles with a plain summary under it — Mon–Fri, Mon, Wed, Fri, Every day. The whole week is visible at once, so a Saturday that is switched on shows without opening anything.

Weekends shaded on the chart

Shaded bands down the board on every non-working day in the company's week. Saturday and Sunday merge into one band so no seam shows. The shading appears at day and week zoom, where a weekend is wide enough to see.

Stage length in working days

The length field says in working days and names the week it is counting on. Type 5 and you get five days of crew on site, not five squares on a calendar. A start dropped on a Saturday rolls forward to the next working day, and the field tells you it did.

WORKING DAYS

See working days
on one of your own jobs.

Twenty minutes, your building, your numbers. Bring the job where “my schedule counts weekends as work days” — we will show you exactly where that stops.

leads2build.com
Laminated columns standing in a post-frame shell
Build Schedule
Project / Task
Hostetler Equipment ShedCrew A
Zimmerman Horse BarnCrew B
PermittingAug 4 – Aug 18
Dirt WorkAug 18 – Aug 22
ConcreteAug 22 – Aug 28
Material DeliveryAug 28 – Sep 1
Post SetSep 1 – Sep 11
Stoltzfus ShopCrew C
Byler BarndominiumCrew A
Jul 27– Aug 2
Aug 3– Aug 9
Aug 10– Aug 16
Aug 17– Aug 23
Aug 24– Aug 30
Aug 31– Sep 6
Sep 7– Sep 13
Sep 14– Sep 20
Sep 21– Sep 27
Sep 28– Oct 4
Oct 5– Oct 11
Oct 12– Oct 18
Oct 19– Oct 25
Oct 26– Nov 1
TODAY
Permitting 4/4
Post Set 3/6
Siding / Roofing 0/11
46% • 38d
Permitting+3d
Concrete
Post Set0/6
Permitting 1/4
Framing 0/6
Siding / Roofing 0/11
Permitting 0/4
Slab / Foundation 0/6
Post Set 0/6
Siding / Roofing 0/11
Shutdown week — Crew B
OVERLAP
Working days — Leads2Build