← THE BLOG

Bill the Draw You Agreed To, Not the One You Remember

SEPTEMBER 17, 2026 · KEITH LEMAY
Truss and steel delivery landing on a post-frame shop pad, the moment the delivery draw comes due

A construction draw schedule that lives in the project manager's head is a loan you did not mean to make. A payment schedule is the agreed split of the contract price into a deposit, one or more draws and a final, written on the estimate the customer approves, carried into the contract unchanged, and turned into an invoice as each stage is earned. It is the difference between billing what was agreed and trying to remember what was said.

How to set one up and turn it into invoices is on the payment schedule feature page.

What a payment schedule is: deposit, draws, final

A payment schedule is three or more dated promises attached to one price. On an $86,000 40x60 shop with 14-foot walls, a 30/40/30 schedule reads: $25,800 on signing, $34,400 when the material lands on the pad, $25,800 when the last trim piece is on. Each line has an amount, a trigger and a status: not yet due, sent, paid.

Two shapes cover nearly every post-frame job:

  • Percentages for the standard shop, garage or hay barn. 30/40/30, 50/50, or 25/25/25/25. The customer reads a fraction and understands it.
  • Fixed dollar draws for the barndominium with a lender behind it. The bank releases money against named events, so the draws are named dollars against named events: $60,000 at dried-in, $45,000 at rough-in, and so on.
Payment Schedule
Payment ScheduleTotals 100%
Standard Payment Cycle (Down:30% / Delivery:60% / Final:10%)Save+ Save as…
1Down30%$26,535.00
2Delivery40%$35,380.00
3Frame Complete20%$17,690.00
4Final10%$8,845.00
+ Add payment stage
Manage presets:Standard Payment Cycle×Half Down×Shop Build 4-Stage×
Percentage draws on a small shop and fixed-dollar draws on a lender-financed build, written the same way. Real screen · sample data.

Why the schedule belongs on the quote, not on the phone

The moment to agree the money is the moment the customer is agreeing the price. A schedule stated on the quote, approved with the quote and carried into the agreement unchanged is the one that never gets argued about at the delivery draw. A schedule agreed on the phone after signing is a negotiation you have to win a second time, with the trusses already ordered.

There is a compliance reason too. Several jurisdictions cap what you may take before work starts. California's Contractors State License Board states that on a home improvement contract the down payment must not exceed 10 percent of the contract price or $1,000, whichever is less. Your state or province has its own rule. A schedule written on the quote is the only version of your terms you can point to when someone asks whether you followed it.

Payment Schedule

Payment Schedule

Payments are tied to build milestones, so you only pay as work progresses.

1
Down (30%)$28,004.55
2
Delivery (60%)$56,009.10
3
Final (10%)$9,334.85
The payment stages on the customer's quote are the same lines that print in the agreement; a preset lands the terms you actually use without re-typing them. Real screen · sample data.

Why post-frame needs draws more than most trades

A post-frame job is front-loaded with material in a way a framing crew's job is not. The posts, the truss package and the steel are ordered, delivered and invoiced to you by the yard before most of the labour has happened. If your delivery draw is not billed the day the truck leaves the pad, you are carrying the yard's invoice on the customer's behalf until somebody remembers.

Weather makes it worse. A two-week rain delay after delivery slips the dried-in stage, and a schedule tied to calendar dates slips the draw with it, even though the material is already sitting on site paid for by you. Tie draws to events, not dates: delivery, dried-in, completion. The build schedule tells you when a stage is actually finished; the payment schedule is what that finish is worth.

What "each stage becomes an invoice" means for the office

Once the schedule is agreed, the office is not deciding what to bill. It is billing what was agreed, when the trigger is met. The delivery draw on the 40x60 is $34,400 because the customer signed a page that said $34,400; the invoice is a copy of that line, not a fresh calculation. That is an easier email to send and an easier one to receive, and it is why invoicing built off a schedule draws fewer questions than invoicing built off a spreadsheet: the customer has already read the line.

New Invoice — payment schedule
Estimate (Job #41208)Locked to this projectHide ▴
Generate 4 invoices from payment schedule
One draft per stage, each with its $ amount pre-filled. Edit + send each separately.
Generate 4
Or pull modular pieces into a single invoice manually:
+ Materials $53,530.00+ Labor $34,920.00+ Customer Total $88,450.00
Payment Schedule (select stages to invoice)+ Insert 1 Stage
✓Down30%$26,535.00
Delivery40%$35,380.00
Frame Complete20%$17,690.00
Final10%$8,845.00
Each stage on the agreed schedule becomes its own invoice when it is earned; the office bills the line, not a number it worked out that morning. Real screen · sample data.

If you are still writing draws by hand, the contractor invoice template that actually gets paid shows what the line has to carry. Inside contractor management software those fields are already filled from the schedule.

What happens when the job changes mid-build

Two things move a schedule after signing, and they must not touch what has already been billed.

  1. A change order. The customer adds a 12-foot lean-to at week three. The extra adjusts the stages still to come, or rides as its own bill, and the two draws already paid stay exactly as they were. A schedule that quietly rewrites paid draws becomes fiction halfway through the job. Pricing the extra so it protects margin is covered in the construction change order that protects your margin.
  2. Estimate drift. Somebody edits the estimate after signature and the total creeps. The schedule bills the signed number and says so, naming both figures and the difference, rather than silently billing the new one.
Change Order — Billing & Delivery
Billing & Delivery$ Amount% of total
1
Doors — deposit at order
$2480.00×
Separate invoice= $2480.00
2
Door install labor
$3200.00×
Merge into existing paymentINV-2026-0038 · Delivery — $35,380.00= $3200.00
3
Balance on completion
$3802.35×
New scheduled payment= $3802.35
+ Add paymentAllocated $9482.35 of $9482.35

Merging into a payment that’s already been sent or paid will automatically append it as a new scheduled payment instead — a billed invoice is never re-charged.

A change order changes the remaining stages, or becomes its own bill; the draws already paid do not move. Real screen · sample data.

The customer can see it the whole time

The schedule is on the quote they approved, in the agreement they signed, and on their project page as the build runs, with paid draws folded away and the next one due at the top. Customers who can see what they have paid and what is next stop ringing to ask, which is the argument made in why contractor management software needs a live customer page. The whole run from quote to that page is the Live Estimate System.

Who a payment schedule fits, and who it does not

It fits any builder who bills a job more than once. That is nearly every post-frame company: the shop over three weeks with a deposit and two draws, the riding arena with four, the barndominium with a lender's six.

It fits the kit supplier too, in a smaller way: deposit on order, balance on delivery is a two-line schedule, and it still stops the balance being forgotten.

It is not much use for a builder paid in full up front on small jobs, or for the company whose lender dictates the draw form so completely that the builder never bills a customer directly. Both can write the schedule for the record, but the invoices will not come off it.

Before you write the next one

  • Decide your default shapes: one percentage schedule for shops and barns, one fixed-dollar schedule for financed homes.
  • Tie every draw to an event you can prove: signing, delivery, dried-in, completion. Never a calendar date.
  • Check your state or province's deposit cap and set the first line under it.
  • Save the shapes as presets so the right one lands on the quote without being chosen.
  • Agree the schedule on the quote. If the customer wants it changed, change it there, before they approve.

What the schedule does not do is chase. It tells you what to bill and when, and it tells the customer what is due. A customer who lets the delivery draw sit for three weeks still has to be phoned by a person, and how often to phone before it becomes a lien question is a decision the software does not make for you.

LEAD · QUOTE · SIGN · INVOICE · BUILD

Build the business,
not just the buildings.

One system from the first call to the final invoice — pipeline, 3D estimates your customer can see, e-sign, deposits, scheduling, change orders and a branded portal.

leads2build.com
A post-frame barndominium at dusk, warm light in every window
The great room of a finished barndominium — exposed timber trusses, a stone fireplace and a wall of windows
Leads2BuildBUILDER OPERATING SYSTEM
A finished post-frame shop with charcoal steel siding and two overhead doors
Leads2BuildBUILDER OPERATING SYSTEM